This table explains important milestones for each round of the Annual Plan Grants (APG) process, from the submission date for letters of intent through the submission of audited financial statements at the conclusion of the reporting period. Each milestone links to process documentation about that event, while links to documents for each round may be found in the body of this table. For more information, you can review the proposal process documentation. See archived rounds.

Milestone 2013–2014 Round 2 2014–2015 Round 1 2014–2015 Round 2 2015–2016 Round 1 2015–2016 Round 2
Letters of intent due 8 November 2013
1 June 2014
1 November 2014
1 July 2015
1 November 2015
WMF assesses eligibility 15 December 2013
Eligibility checklist
15 July 2014
Eligibility checklist
15 January 2015
Eligibility checklist
15 July 2015
Eligibility checklist
15 January 2016
WMF confirms eligibility 15 March 2014 15 September 2014 15 March 2015 15 September 2015 15 March 2016
Proposals due
Proposal form
1 April 2014
1 October 2014
1 April 2015
1 October 2015
1 April 2016
Community review until 30 April 2014 31 October 2014 30 April 2015 30 October 2015 30 April 2016
Staff assessments due
Assessment form
8 May 2014
Assessments
8 November 2014
8 May 2015
Assessments
8 November 2015
8 May 2016
Deliberations 21 May 2014 15 November 2014 14 May 2015 21 November 2015 21 May 2016
FDC recommendation due 1 June 2014
FDC recommendation
1 December 2014
FDC recommendation
1 June 2015
FDC recommendation
1 December 2015
1 June 2016
Board decision due 1 July 2014
Board decision
1 January 2015
Board decision
1 July 2015
1 January 2016
1 July 2016
Appeals and complaints until 8 June 2014 8 December 2014 8 June 2015 8 December 2015 8 June 2016
Progress reports Q1 due 30 October 2014
not required not required not required not required
Progress reports Q2 due 30 January 2015
30 July 2015
30 January 2016
30 July 2016
30 January 2017
Progress reports Q3 due 30 April 2015
not required not required not required not required
Impact reports due 28 September 2015 30 March 2016 28 September 2016 28 March 2017 28 September 2017
Financial statements due 28 October 2015 28 April 2016 28 October 2016 28 April 2017 28 October 2017